Baia wind farm

Grid connection - Baia Wind Power Plant (110 kV OHL, 110 kV UGL and optical fibre installation)

The project covered the design, manufacturing, supply, testing, packaging, transport and site delivery of the equipment and materials, as well as the execution works for the 110 kV OHL and 110 kV UGL to connect the Baia wind farm into the 110/20 kV Baia substation.

The construction and installation works carried out within the project were: foundation execution, erection of towers and cross-arms, insulator strings, earthing installations, installation of junction boxes, installation of the optical fibre and installation of the termination boxes.