Sarichioi wind farm
Connection to the National Power Grid of the Sarichioi Wind Power Plants - Tulcea
The project consisted of building a 15 km overhead power line (OHL) between the electrical substation of the Sarichioi wind farm and the connection point to the National Power Grid, located along the route of the 110 kV overhead line between Zebil and Tulcea Vest, and building the 110/33 kV electrical substation, which was connected to the 110 kV Zebil - Tulcea Vest OHL through an overhead connection.
Total installed capacity: 30 MW
Connection substation - Zebil Nord 110 kV
12 km 110 kV OHL
12 km OPGW
Connection to the Power Transmission and Distribution Grid